Projects

Largest Completed Reference Projects:

Space Fence Surveillance System

at Bucholz Army Airfield on Kwajalein Atoll, the Republic of the Marshall Islands. This project was managed by Donald Pittser, TAB & Cx Supervisor. The combined TAB and Commissioning contract was over $1,449,000. This project was completed in 2018 for Lockheed Martin, AMEC/Foster Wheeler/Woods.

#projects

#reference

4bbdb21b-98bc-43e7-9e13-e473aa1365f3

The Children’s Hospital

l in Aurora, CO was managed by Bryan Hund, TAB Supervisor. This is single largest construction project built at one time in Colorado at the time of build. This hospital complex was completed in November 2007 for Phipps / McCarthy, a joint venture at $770,000. The engineering firm was BR+A / Cator, Ruma & Associates.

#projects

#reference

Childrens Hospital

Notable Completed Reference Projects:

2023

University of Colorado Bear Creek Apartments, Timberline Mechanical $67 Million

2022

Repair Air Passenger Terminal Building 80 at Yokota Air Base Japan, Gilbane $27.5 Million

2021

Central Reference BSL-3 Laboratory Remediation Baku, Azerbaijan, Jacobs / Koray Kilic

2021

Pikes Peak High Altitude Army Research Laboratory 14,111’ Elevation, Olson P&H $7.2 Million

2020

Fort Carson SOF Battalion Operations Regional Support Element, Tepa $52 Million

2019

SHIELD 5 Military Bases 5 & 7, Qatar (46 Buildings), Al Seal / AICI $290 Million

2018

Space Fence Bucholz Army Airfield, Kwajalein Atoll, Marshall Islands, AMEC/Woods $1.6 Billion

2017

United Airlines Consolidated Flight Training Phase One and Two, Murphy Mechanical $40 Million

2016

Central Reference BSL-3 Laboratory Almaty, Kazakhstan, AECOM $150 Million

2015

Al Udeid Air Base, Qatar BPC Phase II & III, Coalition Compound (25 Buildings)

2014

Bagram Air Base, Afghanistan Coalition Operation Center CH2M Hill 100,000 Sq. Ft.

2013

Bagram Air Base, Afghanistan JOC at SOF Complex Phase 1 & 2 (12 Buildings)

2012

2 Bagram Air Base, Afghanistan Fuels, Troop Housing, SOF Complex, $100 Million

2011

Nellis Air Force Base Retro-Commissioning Las Vegas, Nevada, $10 Million.

2010

Central Reference BSL-3 Laboratory Republic of Georgia, Bechtel, $140 Million

2009

9 St. Mary’s Hospital, Dunham Associates, FCI/McCarthy JV, $148 Million

2008

Delta Memorial Hospital, MKK, 2H Mechanical, $113 Million

2007

Children’s Hospital, Cator, Ruma and Associates, Phipps/McCarthy JV, $460 Million

2006

Denver Convention Center Hotel, A. E. and Associates, RK Mechanical, $285 Million

2005

5 Inn of the Mountain Gods Casino, Womer Associates, Southland Industries, $160 Mill

2004

Colorado Convention Center Expansion, ME Engineers, Trautman & Shreve, $310 Mill

2003

Union Plaza Towers, The Ballard Group, Southland Industries, $107 Million

2002

Wellington E. Webb Building, BCER Engineering, Southland Industries, $124 Million

2001

TSA Laboratories, First Choice Heating & Air, Longmont, CO $3 Million

2000

First National Bank, Commercial Systems Integrators, Loveland, CO $10 Million